Add or update tasks in bulk
You can add or update tasks and associated costs in Object and Activity records with the Bulk Task Update tool.
Add tasks and costs
-
Go to the Tools menu and click Bulk Task Update.
-
Make sure that Add New Tasks & Costs is selected.
-
In Datafile, select the file to update. For example, select Object.
-
Under Record Selection, enter the records with one of these options:
-
In Records to be updated, enter the records manually.
-
In List Name, enter a list or click
Options to select it from Portfolio.
-
-
Under New Tasks & Costs, enter the details such as Task, Person, Due Date, and Costs.
-
Click OK.
-
Select a report type and destination and click OK.
Update existing tasks and costs
-
Go to the Tools menu and click Bulk Task Update.
-
Select Update Existing Tasks.
-
Click Search to retrieve Diary records to update.
-
Under Replace Diary with, enter the details such as Person, Date Due, and State.
-
Click OK.